PROJECT PROGRESS UPDATE – HOANG HUY COMMERCE H2, HAI PHONG (APRIL 2026)

   April 17, 2026

      The Hoang Huy Commerce H2 construction investment project is a key mixed-use development comprising commercial, service, and high-end residential apartments in Le Chan Ward, Hai Phong, and is transforming the urban landscape day by day. 

 

     To date, construction activities have been actively expedited, with notable progress in the following areas:

 

  • Substructure works: 100% completion of piling works and diaphragm wall construction.
  • Superstructure works: Completion of columns at Level 2 and the slab at elevation +9.2m.
  • Transfer beam system: Completion of concrete casting for transfer beams at elevation +10.60m (Level 3 area).

 

     Alongside accelerating construction progress, occupational safety, environmental sanitation, and fire prevention and protection are always prioritized. All construction activities strictly comply with approved technical standards and design specifications, ensuring the long-term quality and durability of the project.